Concordia & JLT Approval Consultant (DMCC Compliant)

Compliance & Documentation Matrix

A complete breakdown of Concordia Authority regulations. Find mandatory documents, submission fees, and NOC procedures for Commercial, Residential, and Industrial fit-out permits in Dubai.

Scroll right to view all property types →
If you are setting up an office or retail space in Jumeirah Lakes Towers (JLT), you must deal with Concordia. As the integrated facilities manager for the entire JLT zone (Clusters A-Z), Concordia controls all physical access, fit-out logistics, and community modifications. You cannot start construction without their No Objection Certificate (NOC). We specialize in the specific "Fit-out Manual" regulations enforced by Concordia and the DMCC (Dubai Multi Commodities Centre). Whether you are renovating a commercial office in a high-rise tower, installing a retail kiosk on the concourse level, or modifying a restaurant layout, we ensure your drawings meet their strict logistical standards. Our team manages the complete JLT approval ecosystem. We handle the **DMCC License coordination**, secure the **Concordia Fit-out Permit**, and arrange the mandatory Third Party Liability (TPL) Insurance documents. We also manage the complex **Work Permits** and Access Cards for your contractors, ensuring your site operations run smoothly without security stoppages.
Detailed table showing Concordia Authority requirements, documents, and NOC status for various property types in Dubai.
Approval Requirement
Restaurant UnitSalon / PolyclinicOffice Fit-outRetail / ShopIndustrial WarehouseVilla (New Build)Villa ModificationSwimming PoolHotel / HospitalityExt. Signage
Documents Required
HSE plan + PTW permit to Work documentsIfIfIfIfIfIfIfIfIfIf
Contractor registration / competency documentsIfIfIfIfIfIfIfIfIfIf
Application / Online formReqReqReqReqReqReqReqReqReqReq
Client / Owner ID & Passport / EIDReqReqReqReqReqReqReqReqReqReq
Trade License (for commercial)ReqReqReqReqReqNoNoNoReqReq
Ejari / Tenancy Contract (if out)ReqReqReqReqReqNoNoNoReqNo
Title Deed / Plot documents (new build)IfIfIfIfIfReqIfReqIfIf
Building Management / Landlord NOCReqReqReqReqReqIfIfIfReqIf
Master Developer NOC (if in community)IfIfIfIfIfIfIfIfIfIf
Consultant Appointment LetterReqReqReqReqReqReqReqReqReqReq
Contractor Appointment LetterReqReqReqReqReqReqReqReqReqReq
Method Statement & Risk Assessment (if required)IfIfIfIfIfIfIfIfIfReq
Existing Drawings Required
Existing approved setting out planReqReqReqReqReqIfReqIfReqIf
Existing approved floor planReqReqReqReqReqIfReqIfReqIf
Existing services drawings (if available)IfIfIfIfIfIfIfIfIfIf
Existing Fire & Life Safety drawings (if available)IfIfIfIfIfIfIfIfIfIf
Proposed Drawings Required
Proposed Architectural drawings (plans/sections/elevations)ReqReqReqReqReqReqReqReqReqReq
Proposed Demolition drawings (if any)IfIfIfIfIfNoIfNoIfNo
Proposed MEP drawings (power/lighting/HVAC/plumbing)ReqReqReqReqReqIfIfReqReqReq
Load Calculation (electrical)ReqReqReqReqReqIfIfIfReqIf
Proposed Structural drawings (if structural works)IfIfIfIfReqReqReqIfIfIf
Finishes / Reflected Ceiling Plan (if out)ReqReqReqReqNoNoNoNoReqNo
Kitchen / Equipment layout (restaurants)ReqNoNoNoNoNoNoNoNoNo
Drainage / Grease trap details (restaurants)ReqNoNoNoNoNoNoNoNoNo
Medical / Salon layout + equipment (clinics/salons)NoReqNoNoNoNoNoNoNoNo
Signage drawings (if signage)IfIfIfIfIfIfIfIfIfReq
NOCs / External Approvals
Dubai Civil Defense (FLS approval if applicable)ReqReqIfReqReqIfIfIfReqIf
DEWA Load / connection approval (if applicable)IfIfIfIfIfIfIfIfIfIf
Food Authority / Food Control (restaurants)ReqNoNoNoNoNoNoNoNoNo
Health Authority approval (clinics/salons)NoReqNoNoNoNoNoNoNoNo
RTA NOC (access/parking/terrace if applicable)IfIfIfIfReqIfIfIfIfReq
Environmental / EHS approval (industrial if applicable)IfIfIfIfReqIfIfIfIfIf
Completion / Final
As built drawings (if required)IfIfIfIfIfIfIfIfIfIf
Completion certificate / Final inspection requestReqReqReqReqReqReqReqReqReqReq
Testing & commissioning reports (FLS/MEP if required)ReqIfIfIfReqIfIfIfReqIf
Photos / completion evidence (if required)IfIfIfIfIfIfIfIfIfIf

Status Legend

Required

Mandatory document for approval

If Applicable

Dependent on project scope

Not Required

Exempt for this category

Need Help with Authority Approvals?

Our expert engineers handle the entire NOC process, ensuring faster approvals and full compliance with Dubai regulations.