RTA Road Closure & Traffic Diversion Permit Dubai 2026
Closing a lane, diverting traffic or occupying a public road for construction in Dubai needs an RTA diversion permit, applied for through the Right-of-Way Permit System (ROWPS). The official fee is small; what delays projects is the diversion drawing and the coordination steps after the permit is issued.
Dar Al Naseeb Engineering Consultants
Licensed Engineering Consultants · Dubai, UAE · Est. 2012
When You Need an RTA Diversion Permit
A diversion permit is needed whenever works inside the public right of way affect traffic, for example:
- Lane closures for utility connections, road crossings or excavation
- Full or partial road diversions during construction
- Crane, concrete pump or delivery set-ups that occupy the carriageway
- Site access works that interrupt traffic flow on an adjacent road
Works that occupy the right of way without affecting traffic still need a ROW permit — see the ROWPS right-of-way permit guide.
Documents Required
- Detailed layout drawings of the diversion, signed and stamped by the contractor, the consultant and the applicant
- Affection plan for the plot — see how to get a DM affection plan
- Building permit copies where the works relate to a permitted project
- Dated photographs of the work zone
- Purchase receipt for the RTA Work Zone Traffic Management Manual
The diversion layout is designed according to the type of work, the number of lanes being closed and the road's speed limit, following the RTA's traffic diversion standards. A layout that does not match the speed class of the road is the most common reason for a resubmission.
Fees and Timeline
ROW permit fee: AED 220
Knowledge and Innovation fee: AED 20
Refundable deposit: where temporary occupation of the right of way requires one
Processing time: 7 working days, which can be extended if other approvals are needed. Two conditions catch applicants out: the application is cancelled automatically if fees are not paid within the specified period, or if a query from the processor is left unanswered for 15 days.
After the Permit: The Steps That Actually Delay Site Start
An issued permit does not mean the road can be closed tomorrow. Before mobilising, the contractor must:
1. Coordinate with Dubai Police and the RTA traffic department
2. Coordinate directly with the RTA inspection section and the right-of-way services section
3. Comply with time restrictions — noise-generating activities near residential areas and heavy-vehicle movements are restricted to permitted hours
Building these coordination steps into the programme is what separates a 2-week closure lead time from a 6-week one. For the wider picture of RTA NOCs, see the complete RTA approval guide.