Trakhees CED vs EHS: Two Departments, Two Different Questions
Trakhees has two departments that matter to most projects. The Civil Engineering Department (CED) decides whether your drawings and works comply. Environment, Health & Safety (EHS) decides whether your facility is fit to operate. Mixing them up is one of the most common reasons a warehouse or fit-out stalls in JAFZA.
Dar Al Naseeb Engineering Consultants
Licensed Engineering Consultants · Dubai, UAE · Est. 2012
CED and EHS side by side, from Trakhees' published procedures.
| Parameter | CED | EHS |
|---|---|---|
| Question it answers | Do the drawings and works comply? | Is the facility safe and fit to operate? |
| Main outputs | Building Permit, Modification Permit, General NOC, completion certificates (BCC, MCC) | Operation Fitness Certificate (OFC), NOC for Activity Verification (NOC-AV), environmental permits |
| Who usually applies | The appointed consultant | The licensee or occupier |
| What triggers it | New construction, modification or fit-out works | Starting or renewing operations in a facility |
| How it is decided | Engineering review of drawings, then site inspections | EHS officer inspects the facility; comments must be closed point by point |
What CED Covers
CED is the engineering authority. Its own procedure says any modification or fit-out to a completed facility that already has a Building Completion Certificate needs a Modification Permit from CED's Modification Section before works start. CED engineers review the drawings against Trakhees' rules, circulars and design guidelines, and stamp them if they comply.
CED also issues:
- General NOCs for grading and levelling, shaded parking, landscaping, machinery foundations, tower cranes, storage tanks and fencing or compound walls
- Facility Permit approval for minor racking or shelving (rack height up to 3.5 m and layout area up to 250 m²) and machinery installed without civil works, under circular CEDGR-85
- Mobilisation NOCs, temporary facility approvals and NOCs for additional DEWA connections
- Completion: the Modification Completion Certificate (MCC) closes a Modification Permit
Two details from the procedure catch people out. A Modification Permit must be revalidated if works do not start within six months. And CED may stamp a permit "with comments", which still have to be complied with on site.
What EHS Covers
EHS is the operations and safety regulator. For most businesses the outputs that matter are:
- Operation Fitness Certificate (OFC), requested through "EHS Services" on the Trakhees portal, as new, amendment or renewal
- NOC for Activity Verification (NOC-AV), also new or renewal
- Environmental permits for air emissions, irrigation and harbour discharge, handled by the EHS Environment Section
The March 2026 guideline sets out the sequence: upload the trade licence and, where you have one, the Building Completion or Modification Completion Certificate. Payment advice arrives within 2 working days. After payment, an EHS officer inspects the facility and issues a report. Every comment has to be answered point by point in the portal's Non-Compliance Tracker until it shows "Completed".
That last point matters at renewal time. Open inspection comments delay the OFC or NOC-AV renewal, and Trakhees says this can affect the renewal of the business licence itself.
When You Need Both, and in What Order
A typical JAFZA warehouse modification touches both departments:
1. CED Modification Permit on the drawings, before any work starts
2. Works on site, with CED inspections
3. Modification Completion Certificate from CED
4. EHS OFC (or amendment) with the completion certificate uploaded, then the EHS inspection
Doing these out of order is where time is lost. An EHS application without the completion certificate, or works started before the CED permit is stamped, both lead to rework. Racking is the classic example: small systems within the CEDGR-85 limits need only a CED Facility Permit, while larger or mezzanine-linked racking needs a full Modification Permit. See our guides to warehouse racking approval, JAFZA EHS inspections and Trakhees completion certificates.
Who Can Submit
CED submissions are made by the client's appointed consultant, and Trakhees requires consultants and contractors working in its jurisdiction to be accredited. You can check a firm on the Trakhees accreditation portal; our accreditation guide explains the categories.
EHS applications are usually made by the business itself, through its registered company account on the same portal. Many occupiers ask their consultant to prepare the responses to EHS inspection comments, because the fixes are often physical: fire exits, storage heights, signage and housekeeping.
For how this fits with the rest of Trakhees, read the Trakhees approvals overview.
Free Assessment
Not Sure Which Department Your Project Needs?
Send us the plot, the licence and the scope. We confirm the CED and EHS steps and the order to do them in. Free review in 24 hours.
Frequently Asked Questions
01What is the difference between Trakhees CED and EHS?
02Do I need a CED permit before EHS approval?
03How long does a Trakhees Modification Permit take?
04What is a Trakhees OFC?
05Does warehouse racking need a CED permit?