Submitting to the wrong authority is the most expensive early mistake in Dubai approvals: the drawings are rejected before anyone reviews the design. Trakhees, Dubai Municipality and DDA each govern different areas, and published lists online disagree. Here is how we route each area, and how to confirm yours.

Dar Al Naseeb Engineering Consultants

Licensed Engineering Consultants · Dubai, UAE · Est. 2012

3 authorities
Trakhees, DDA and Dubai Municipality
Plot first
The plot, not the developer, decides
No official list
Found from Trakhees
3 authorities
Trakhees, DDA and Dubai Municipality
Plot first
The plot, not the developer, decides
No official list
Found from Trakhees
Before design
When to confirm the route
Three bodies issue building permits across most of Dubai: Trakhees, the regulator of the Ports, Customs and Free Zone Corporation, in its zones; the Dubai Development Authority in its areas; and Dubai Municipality on most of the mainland. Each uses its own drawing format and portal, so the authority decides how the drawings are prepared, not just where they are sent. Lists published online contradict each other, especially on Nakheel communities such as JVC and JVT. We could not find an official consolidated list from Trakhees. The table below shows how our own community guides route each area. For any specific plot, confirm the authority before design starts.
As Set Out in Our Community Guides

Confirm for your plot. Some sources route JVC, JVT and other Nakheel areas differently.

AreaDeveloper layerBuilding permit from
Palm JumeirahNakheelTrakhees
Palm Jebel AliNakheelTrakhees
Jumeirah Islands, Jumeirah Park, Al FurjanNakheelTrakhees
Jumeirah Golf EstatesJGE ARCTrakhees
JAFZA, Jebel Ali IndustrialNot applicableTrakhees
Dubai Maritime CityDMC AuthorityTrakhees
JVC and JVTNakheelTrakhees (some sources say Dubai Municipality)
Dubai Hills Estate, Emirates Hills, DAMAC Hills 1Emaar or DAMACDDA
Arabian RanchesEmaarDDA
The Springs, The MeadowsEmaarDubai Municipality
01

Why Published Lists Disagree

Online lists conflict for three reasons. Communities sit under one master developer but more than one authority; master plans have changed over time; and many lists are copied from each other without checking. One consultant puts JVC and JVT under Trakhees, another under Dubai Municipality, and a third under DDA.

A wrong route is not a small error. Trakhees reviewers routinely reject drawings prepared in Dubai Municipality's format, and a submission to the wrong portal is returned before technical review.

02

How to Confirm Your Plot's Authority

Use the plot's own records, not a list:

  • The affection plan or site plan for the plot
  • Previous permits and completion certificates for the property, which name the issuing authority
  • The master developer's modification guidelines, which name the authority their NOC feeds into

Once confirmed, the developer NOC and authority permit follow in order. For Trakhees areas, see the Trakhees approval process. For DDA, see the DDA approval process.

03

Community Guides

Free Assessment

Not Sure Who Approves Your Plot?

We confirm the authority from your plot records before any drawing is paid for. Free check in 24 hours.

Frequently Asked Questions

01Which areas are under Trakhees in Dubai?
Trakhees issues building permits in its zones, including Palm Jumeirah, JAFZA and Nakheel communities such as Jumeirah Islands, Jumeirah Park and Al Furjan, as well as Dubai Maritime City. We found no official consolidated list, so confirm your plot's authority from its own records.
02Is Palm Jumeirah under Trakhees or Dubai Municipality?
Palm Jumeirah villa works follow the Nakheel NOC and then a Trakhees permit.
03Is JVC under Trakhees?
Trakhees. Published sources disagree, some saying Dubai Municipality or DDA, but our own completed permits in JVC, for pools, villa modifications and a clinic fit-out, were issued by Trakhees after Nakheel's consent.
04What happens if I submit to the wrong authority?
The submission is returned, often before technical review, and drawings may need reformatting, since Trakhees and Dubai Municipality use different drawing formats.
05How do I check which authority approves my property?
Look at the plot's affection plan or site plan, previous permits or completion certificates for the property, and the master developer's modification guidelines.

Official Sources

Fees and procedures change without notice. Confirm any figure with the authority before you rely on it.