JAFZA works are approved by Trakhees, through its engineering and EHS departments. Most refusals trace back to six causes, and nearly all of them are decided before the first drawing is sent.

Dar Al Naseeb Engineering Consultants

Licensed Engineering Consultants · Dubai, UAE · Est. 2012

Trakhees
Approves works in JAFZA
CED + EHS
Two tracks to satisfy
6 causes
Behind most refusals
Trakhees
Approves works in JAFZA
CED + EHS
Two tracks to satisfy
6 causes
Behind most refusals
Accredited
Companies working on Trakhees projects
In JAFZA, building and fit-out permits come from Trakhees' Civil Engineering Department, and operational safety from its Environment, Health and Safety department. Applications come back for a small set of reasons, most of which are about order and format rather than design.
01

The Six Causes

1. Drawings in Dubai Municipality format. Trakhees uses its own format, and DM-format drawings are routinely rejected.

2. Racking installed before approval. Structural racking needs approval first. See racking approval.

3. Mezzanines without structural and fire updates. See mezzanine approval.

4. EHS left until after the building permit. Operational requirements affect layout, so plan them together. See JAFZA EHS.

5. Dangerous goods not declared at design stage, which changes fire and storage requirements.

6. Unaccredited staff on the submission. Companies with projects under Trakhees must follow its accreditation requirements. See Trakhees accreditation.

02

Next Steps

For the full process, see JAFZA warehouse approval. When leaving a unit, see JAFZA vacating and handover.

Free Assessment

JAFZA Application Came Back?

We fix the format, sequence and documentation, and resubmit once. Free review in 24 hours.

Frequently Asked Questions

01Why was my JAFZA application rejected?
Most often because drawings were in Dubai Municipality format, racking or a mezzanine was installed before approval, EHS was left late, or dangerous goods weren't declared.
02Who approves works in JAFZA?
Trakhees: its Civil Engineering Department for building and fit-out permits, and Environment, Health and Safety for operations.
03Can I install racking in a JAFZA warehouse before approval?
Structural racking should be approved before installation. Installing first is a common cause of refusal and rework.