DDA Fit-Out Permit or Building Modification Permit? Choosing Correctly
In DDA areas, the same office or villa job can need two very different permits. DDA's own rule is blunt: if a fit-out application should have been a modification, the fit-out fee is not refunded. Here is how to tell which one you need.
Dar Al Naseeb Engineering Consultants
Licensed Engineering Consultants · Dubai, UAE · Est. 2012
Each plus AED 20 in transaction dirhams.
| Item | Fit-Out Permit | Building Modification Permit |
|---|---|---|
| Covers | Fit-out of any part of a building | Structural additions, change of use, extra GFA |
| Fee | AED 0.90/ft², min 200, max 10,000 | AED 1.0/ft² of additional or relevant area |
| Service time | 2 working days | 2 working days |
| Validity | 6 months | Renewable, AED 200 per 3 months up to 1 year |
| Available | Any time, with owner NOC | After the building completion certificate |
| Completion | Civil Defence completion first | Per permit conditions |
Quick Test: Which One Is Yours?
Ask three questions:
- Are you adding or changing structural elements, such as beams, slabs or a mezzanine?
- Are you changing the use, for example office to clinic or café?
- Are you adding floor area?
A yes to any of these points to a building modification. If all three are no, it is usually a fit-out. Small cores under 200 mm are allowed in a fit-out if they avoid structural elements such as tendons and stay at least 1 m from columns, according to DDA.
Related Guides
Free Assessment
Choose the Right DDA Permit First Time
We check your scope against DDA's rules before anything is submitted or paid. Free check in 24 hours.
Frequently Asked Questions
01When do I need a DDA building modification permit?
02Does DDA refund the fit-out fee if I chose the wrong permit?
03How much is a DDA building modification permit?
04Can I core through a slab under a DDA fit-out permit?
Official Sources
Fees and procedures change without notice. Confirm any figure with the authority before you rely on it.