Dubai Development Authority·5 min read·

DDA Documents by Permit Type: The Official Lists Side by Side

Fit-OutBuilding ModificationShoringDemolitionFeesTimes

DDA publishes a separate document list for each permit. Using the fit-out list for a modification, or missing one NOC, is how applications stall. Here are DDA's own lists, side by side.

Dar Al Naseeb Engineering Consultants

Licensed Engineering Consultants · Dubai, UAE · Est. 2012

4 permits
Each with its own document list
Contractor
Applies for each permit
Circular 400
Drawing format DDA requires
4 permits
Each with its own document list
Contractor
Applies for each permit
Circular 400
Drawing format DDA requires
AED 20
Knowledge + Innovation dirhams per transaction
The Dubai Development Authority publishes each permit as a separate service with its own required documents, fees and service time. All four permits below are applied for by the contractor, online through DDA's Zoning e-Services. For the overall DDA process, see the DDA approval process. This page focuses on getting the document set right for the specific permit.
From DDA's Service Pages

Plus AED 10 Knowledge Dirham and AED 10 Innovation Dirham per transaction.

PermitFeeService time
Fit-Out PermitAED 0.90/ft², min 200, max 10,0002 working days
Building Modification PermitAED 1.0/ft² of relevant area2 working days
Shoring PermitAED 0.05/ft² of total BUA3 working days
Demolition PermitAED 1,000 per unit per floor5 working days
01

Fit-Out Permit

  • Contractor appointment letter from the tenant
  • Copy of Ejari
  • NOC from the building owner
  • NOCs from relevant authorities, per DDA's NOC matrix
  • Approved stamped drawings and proposed drawings, in Circular 400 format

Where the building has no completion certificate yet, DDA also requires NOCs from the main contractor, main consultant and plot owner. The permit is valid for 6 months.

02

Building Modification Permit

  • Appointment letter signed by owner, consultant and contractor
  • Layout of site mobilisation, if applicable

This is the route for adding structural elements, changing the use or adding GFA, and it is available after the building completion certificate. See fit-out vs building modification.

03

Shoring and Demolition Permits

Shoring: soil investigation report, appointment letter, geotechnical calculations and model, shoring drawings in Circular 400 format, design review checklist, NOCs where applicable, a neighbour's NOC if anchors enter their plot, and a third-party review for more than 3 basements or projects near water. Preliminary Design Approval comes first. See shoring permits.

Demolition: site setting-out plan, NOCs (DEWA and telecom for mechanical demolition; Civil Defence, Police and RTA added for controlled explosion), hoarding layout, method statement with HSE and emergency plan, a neighbour impact study and site photographs. See demolition permits.

Free Assessment

Get the DDA File Complete First Time

We prepare Circular 400 drawings and the full document set for the right permit. Free scope check in 24 hours.

Frequently Asked Questions

01What documents does a DDA fit-out permit need?
A contractor appointment letter from the tenant, Ejari, the building owner's NOC, relevant authority NOCs and approved and proposed drawings in Circular 400 format. Buildings without a completion certificate also need NOCs from the main contractor, main consultant and plot owner.
02What documents does a DDA building modification permit need?
An appointment letter signed by the owner, consultant and contractor, and a site mobilisation layout where applicable.
03Who applies for DDA permits?
The contractor, online through DDA's Zoning e-Services, with drawings prepared by the consultant.
04How long is a DDA fit-out permit valid?
Six months, according to DDA's service page.