Shoring and Excavation Permits in Dubai 2026
Dubai's building bylaw requires a shoring system in excavations deeper than 2 m, and shoring needs its own permit before the building permit stage is complete. DDA publishes exact fees and documents; Dubai Municipality handles it through its site preparation service.
Dar Al Naseeb Engineering Consultants
Licensed Engineering Consultants · Dubai, UAE · Est. 2012
These figures are DDA's. Confirm Dubai Municipality's charges at application.
| Item | DDA requirement |
|---|---|
| Permit fee | AED 0.05 per ft² on total BUA, deducted from the final building permit |
| Renewal | AED 0.03 per ft² per month requested, maximum AED 6,000 per month |
| Prerequisite | Preliminary Design Approval |
| Applicant | Contractor, online through Zoning e-Services |
| Third-party review | Geotechnical peer review for more than 3 basements, or special projects near water bodies |
Documents Required for a Shoring Permit
DDA's list is the most complete published reference:
- Soil investigation report
- Appointment letter signed by owner, consultant and contractor
- Geotechnical design calculations (slope stability) for open excavation
- Geotechnical model
- Shoring design drawings, in Circular 400 format
- Shoring design review checklist
- NOCs from relevant authorities, where applicable
- NOC from the neighbour or plot owner if excavation or anchors enter the neighbouring plot
- Third-party geotechnical peer review, where triggered
The neighbour NOC deserves early attention. Anchors crossing a boundary turn a technical matter into a negotiation with another owner, and that timeline is outside your control. If the NOC looks unlikely, redesign without anchors before you submit.
Shoring Design Basis
The bylaw's excavation shoring provisions name Eurocode 7 and BS 8081 among the design codes. Works close to protected road zones, including excavation, piling, shoring and foundations, must also observe the legislation on roads and public transport.
That second point is why roadside basements often need RTA involvement. See utility NOCs and the ROWPS right-of-way permit.
Groundwater and Inspection on Site
Dubai Municipality's directory shows two services worth building into the programme:
- NOC to discharge groundwater into temporary lagoons, needed before construction starts, within 5 days
- Request site structural inspection, for shoring works after excavation at key levels, through the DM website or BPS, free if no re-demarcation is needed
High groundwater is common near the coast and creek. If dewatering is likely, budget and programme it from the start rather than discovering it during excavation.
Where Shoring Sits in the Permit Sequence
A typical order for a new building is affection plan, soil investigation, preliminary design approval, shoring permit, excavation, then the main structure under the building permit. In DDA areas, the shoring fee already paid is deducted from the final building permit, so it is not a pure additional cost.
Free Assessment
Going Below Ground? Get the Shoring Route Right
We coordinate the soil report, shoring design, neighbour NOCs and permit submission so excavation starts on programme. Free assessment in 24 hours.
Frequently Asked Questions
01When is shoring required in Dubai?
02How much does a shoring permit cost in Dubai?
03How long is a shoring permit valid?
04Do I need my neighbour's approval for shoring anchors?
05When does shoring need a third-party review?
06Can excavation start before the shoring permit?