Steel Structure Drawings and Calculations in Dubai
Sheds, mezzanines, canopies, platforms and pergolas are all structures. Their approval rests on a structural design to recognised codes, and the fabricator's drawings have to match it. This is what each document is and who prepares it.
Dar Al Naseeb Engineering Consultants
Licensed Engineering Consultants · Dubai, UAE · Est. 2012
The Design Codes
In Dubai Municipality, Administrative Resolution No. 37 of 2021 sets the accepted structural codes. For steel it lists, among others:
- AISC 360, Specification for Structural Steel Buildings
- AISC 341, Seismic Provisions for Structural Steel Buildings
- AWS D1.1, Structural Welding Code: Steel (with D1.4 and D1.8)
- ASCE 7 for loads, and MBMA for metal building systems
- Eurocode 3 and BS 5950 as European and British alternatives
The resolution says steel structures must be designed to the latest editions of these American, European or British codes. Mixing codes within one design is a common reason for comments.
The Documents, in Order
1. Structural calculations: loads, member and connection design, stability and the supporting structure or foundations
2. Structural drawings: framing plans, sections, member sizes, base plates and anchors, general notes with codes and material grades. These are what the authority stamps
3. Shop (fabrication) drawings: every member and plate with exact dimensions, holes, welds and marks, prepared for the fabricator
4. Connection details: bolted and welded joints, designed or checked by the engineer
5. Erection drawings: the assembly sequence and member marks on site
6. Inspection and completion records: material certificates, weld and bolt inspections, and the authority's completion certificate
Steps 3 to 5 must stay consistent with the approved design. If the fabricator changes a section or a connection, the engineer has to check and, where required, resubmit.
Fabricators, Erectors and Inspections
Dubai Municipality's standard DMS 35:2020 sets requirements for organisations that design, manufacture, fabricate and erect steel structures, including quality management, factory production control and conformity certification. When you compare fabricators, ask how they meet it.
Dubai Municipality issued Circular 242 of 2020 on steel industrial buildings up to ground plus one floor, and carries out inspections on steel structures for taller multi-storey buildings. In Trakhees areas, minor racking up to 3.5 m high and 250 m² is handled by a CED Facility Permit, while larger steel works need a Modification Permit. See racking approvals.
Erection Methodology
The erection method statement explains how the approved structure will be put up safely and in the right order. It is prepared by the erector and checked against the design. It normally covers:
- Sequence: which frames go up first, and when the structure becomes stable on its own
- Temporary bracing until permanent bracing, decking or connections are complete
- Lifting plan: crane or lifting equipment, loads and exclusion zones. Lifting equipment in Dubai is covered by Dubai Municipality's guideline DM-HSD-GU48 on examination and certification of lifting equipment
- Bolting and welding on site, with the inspection and testing to be done
- Tolerances and survey of column positions and levels before and after erection
On an existing building, such as a new mezzanine in a working warehouse, the method statement also covers how the work is separated from operations and how loads reach the existing slab.
Common Steel Projects
- Mezzanines in warehouses. Administrative Resolution No. 37 of 2021 sets a minimum live load of 5 kN/m² for mezzanine floors. See mezzanine approvals
- Sheds and canopies on industrial plots
- Platforms and staircases for plant and access
- Pergolas and shades on villas: pergola permits
- Structural changes to existing buildings: structural modifications
Our portfolio lists 15 permit records involving steel or mezzanine works. See the project portfolio.
Free Assessment
Planning a Steel Structure?
Send us the plot, the use and a sketch. We confirm the authority, the codes and the documents needed before fabrication starts. Free review in 24 hours.
Frequently Asked Questions
01Which code is used for steel design in Dubai?
02What is the difference between structural drawings and shop drawings?
03Does a steel shed need a building permit?
04Can the design consultant also fabricate the steel?
Official Sources
Fees and procedures change without notice. Confirm any figure with the authority before you rely on it.
- Administrative Resolution No. (37) of 2021: Building Requirements and Specifications
- Dubai Municipality: building regulation publications (incl. DMS 35:2020, steel structures)
- Dubai Municipality: Building Permit Procedures
- Trakhees CED: Client Procedure for Modification Permits (PCFC-TRK-CED-MF-CP-01, Sep 2024)
- Dubai Municipality: DM-HSD-GU48 lifting equipment guideline (PDF)